3-20-2010 Pictures: Habitat for Humanity Nissan Build

 

Devotional (7:40 am)

 

Plumb walls and brace outside walls for trusses (8:49 am)

 

Nailing outside OSB on studs

 

Inside walls built and up (9:10 am)

 

Ladies nailing outside walls

 

Workers

 

Crane ready to set trusses

 

Move half of trusses off stack for far half of home (9:44 am)

 

End truss installed (10:44 am)

 

Trusses installed by lunch (11:39 am)

 

End of day - all trusses and most of the 2X6 sub facier installed (3:36 pm)

 