Day 1: 100%--Floor joists and sub flooring
March 6 100%--Framing of exterior walls
100%--Sheeting on exterior walls
Lunch by: Liberty Cumberland
Devotional by: Liberty Cumberland
Work Groups: WCHS Football Team; Gath Baptist
Day 2: 100%--Set trusses and build truss ends
March 13 100%--Install decking on roof
(Rain- 100%-- Frame interior walls
Out) 100%--Wrap house
100%--Put facia boards on rafters
100%--Set bath tubs
Lunch by: McM Area Youth Min
Devotional by: McM Area Youth Min
Work Groups: Keith Bouldin; Eddie Ware- McM Area Youth Min
Day 3: 100%--Start roofing (this may need to be continued on the following weekend)
March 20 100%--Install windows and doors - Breakfast and Noon Rotary Clubs
Start hanging vinyl siding
100%--Lay water & septic lines (if not already done)
100%-Plumbing rough-in
100%-Electrical Rough-in
Lunch by: Pearls of Christ
Devotional by: Pearls of Christ/ Central Baptist
Work Groups: Pearls of Christ/ Central Baptist
Day 4: 100%--Finish roofing
March 27 ~95%--Continue hanging vinyl siding
100%--Plumbing pressure check – verified pressure leak free before sheetrock installed
100%--Electrical Rough-in
Lunch by: Youth Ministries
Devotional by: Youth Ministries
Work Groups: JROTC-WCHS; Yorozu; Youth Ministries
Electrical inspection: When inspection passes, ceilings and walls will be insulated professionally.
Sheet rock hung (100%) and finished (~50%) after insulation installed – between March 27 – April 10?
Day 5: April 3 No work! Easter weekend. No work
Day 6: 100%--Paint interior walls
April 10 100%--Lay plastic under house
Build front porch railing and set porch posts
100%--Paint trim prior to installing
Catch up on any unfinished items to this point
Lunch by: First Methodist
Devotional by: Covenant Fellowship
Work Groups: Covenant Fellowship; Morrison First Baptist; First Methodist
Install vinyl flooring and install kitchen and bathroom cabinets between April 10 & April 17.
Day 7a: Touchup paint interior walls
April 17 Hang doors and start installing baseboards
Paint doors prior to re-hanging
~40%-Build side porch and finish front porch
Lunch by: St. Catherine
Devotional by: St. Catherine
Work Groups: Central Baptist; St. Catherine
Day 7b Sunday - April 18 Seventh Day Adventist
Day 8: Finish installing baseboards
April 24 Caulk baseboards
Finish side porch and front porch
Lunch by: First Baptist
Devotional by: First Baptist
Work Groups: First Baptist, First National Bank
Day 9 Set fixtures
May 1 Finish caulk around baseboards
Touch up paint on trim
Lunch by: Christ United Methodist
Devotional by: Christ United Methodist
Work Groups: Christ United Methodist; Leadership McM/Warren; Central Church of Christ
Day 10: May 8 No work! Mother’s Day Weekend. No work unless needed due to rain.
Day 11: Install closet rods and shelves
May 15 Set appliances
Install towel bars
Lunch by: River Park
Devotional by: Tim King
Work Groups: River Park; Smartt Assembly
Landscaping can be done May 15 or May 22. This includes grass seed and foundation planting.
Day 12: Finish plumbing and electrical (hang lights and install plumbing fixtures)
May 22 Install wall plugs, phone jacks and light switches
Start work on punch list
Lunch by: Bates Hill
Devotional by: Bates Hill
Work Groups: Bates Hill
Day 13: May 29 No work! Memorial Weekend. No work unless needed due to rain.
Day 14: Complete items on punch list
June 5 Hang blinds
Touch-up paint
Lunch by: Shepherd-Lutheran
Devotional by: Shepherd-Lutheran
Work Groups: WCHS Cheerleaders; Shepherd-Lutheran
Day 15: Hang storm doors
June 12 Clean up house
Wash windows
Pick up yard and anything else that has not been completed
Lunch by: First Baptist
Devotional by: First Baptist
Work Groups: First Baptist; Master Gardeners Club
Day 16: June 19 No work! Father’s Day Weekend. No work unless needed due to rain.
Day 17: June 26 No work! No work unless needed due to rain.
Day 18: July 3 No work! July 4 Weekend.
Day 19: July 10 No work! unless needed due to rain.
Dedication will be held at 10:00 A.M. on Saturday, July 17, 2009
NOTE: Rain out days will be made up on following weekends – dedication could be pushed out past July 17
Dedication will not occur until home has been completed and completion check list signed off by homeowner
![]()