2011 Building Schedule for 2nd Habitat Ebonwood House
(Cherry Family)

 

Cap installed and floor joists hung by Habitat crew prior to begin of build.

Day 1:  April 9

           Floor joists and sub flooring
          Framing of exterior walls
         Sheeting on exterior walls
           Lunch by: Liberty CPC
                        Devotional by: Liberty CPC & West. Church of Christ
                        Work Group from: Gath Baptist, St. Catherine & WCHS Football

Day 2: April 16

            Set trusses and build truss ends
       Install decking on roof
         Frame interior walls
       Wrap house
              Put facia boards on rafters
            Set bath tubs
                        Lunch by: Ben Lomand Tele. & Yorozu Automotive
                        Devotional by:
                        Work Group from: Ben Lomand Tele. & Yorozu Automotive

April 23 Easter – no work unless needed to make up rain day

Day 3: April 30 

            Start roofing (this may need to be continued to the following weekend)
          Install windows and doors - Breakfast and Noon Rotary Clubs
                        Start hanging vinyl siding.
                        Lay water & sewer lines (if not already done)
                        Plumbing rough-in (professional + helper volunteers)
                        Lunch by: Central Baptist Assn., Covenant Fellowship, First United Methodist
                        Devotional by: Covenant Fellowship & Morrison First Baptist
Work Group from: Central Baptist Assn., Covenant Fellowship, First United Methodist & Morrison First Baptist

May 7 Mother’s Day – no work unless needed to make up rain day

Day 4A:  May 14

        Finish roofing     
            Continue hanging vinyl siding          
                        Electrical Rough-in (professional + helper volunteers)
                        Lunch by: First Baptist
                        Devotional by: First Baptist
                        Work Group from: Bridgestone Union, First Baptist, WCHS Cheerleaders & WCHS Golf

Day 4B:  May 15

        Finish roofing         
           Continue hanging vinyl siding        
                        Electrical Rough-in (professional + helper volunteers)
                        Lunch by: Seventh Day Adventist
                        Devotional by: Seventh Day Adventist
                        Work Group from: Seventh Day Adventist

Electrical inspection: When inspection passes, ceilings will be insulated professionally.

Day 5: May 21

            Insulate walls (professional)
            Lay plastic under house
Build front porch railing and set porch posts
                        Catch up on any unfinished items to this point
                        Lunch by: Oster
                        Devotional by: Oster
                        Work Group from: Bridgestone Union & Oster
                                 
Day 6: May 28  

           Paint interior walls         
  Paint trim prior to installation
                        Lunch by: Pioneer Comm & SOTH Lutheran
                        Devotional by: Pioneer Comm & SOTH Lutheran
                        Work Group from: Covenant Fellowship, Christ United Methodist, Pioneer Comm &
SOTH Lutheran
  
Day 7: June 4

            Finish painting interior walls            
       Start installing baseboards and hang doors
                        Lunch by: Christ United Methodist & First Baptist
                        Devotional by: Christ United Methodist & First Baptist
                        Work Group from: Christ United Methodist & First Baptist

Install vinyl flooring and install kitchen/bathroom cabinets between June 4 and June 11.
           
Day 8: June 11

            Set fixtures
            Finish baseboard installation and hang doors
               Caulk around baseboards
             Paint trim
                        Lunch by: Pioneer Comm.
                        Devotional by: Pioneer Comm.
                        Work Group from: Master Gardeners & Pioneer Comm.

Day 9: June 18 Dad’s Day

            Install closet rods and shelves
            Caulk around baseboards (if not already done)
       Paint trim
           Set appliances
           Install towel bars
               Lunch by: River Park
                       Devotional by: River Park
                       Work Group from: Bridgestone & River Park

Day 10: June 25

          Finish plumbing and electrical (Hang lights and install plumbing fixtures)
            Install wall plugs, phone jacks and light switches
                        Start work on punch list
                        Lunch by: Calvary Worship Ctr.
                        Devotional by: Calvary Worship Ctr.
                        Work Group from: Calvary Worship Ctr.

July 4 weekend – no work
           
Day 11: July 9

          Complete items on punch list
               Hang blinds
Touch up paint
                        Plant trees and landscape
                        Yard work (plant grass or lay sod)